DISCLAIMER: TRADITION LIEN SERVICE, a Division of Tradition Software, Inc. makes no warrant, express or implied for the use of this website. In no event shall TRADITION LIEN SERVICE be liable to anyone for any problem, claim or loss arising out of the use of TraditionLienService.com. TRADITION LIEN SERVICE is not engaged in practicing law nor does TRADITION LIEN SERVICE provide legal advice in the state of Mississippi.

1ST NOTICE
Commercial Existing Residential New Residential
Preliminary Notice Preliminary Notice Preliminary Notice

On private Commercial projects MISSISSIPPI Code Mississippi Code § 85-7-407 (2) requires a Preliminary Notice must be served to all legal parties on a project (Customer, Owner, General Contractor, Lender) within thirty (30) days following the first delivery of labor, services or materials to the property, either by e-mail with a confirmed receipt, registered or certified mail, or statutory overnight delivery.

TRADITION LIEN SERVICE can research and send this notice on your behalf for only $27. Or, you can print this MISSISSIPPI notice and others by purchasing PreLien2Lien from TRADITION SOFTWARE for as little as $164.

On Existing Residential projects MISSISSIPPI Code Mississippi Code § 85-7-407 (2) requires a Preliminary Notice must be served to all legal parties on a project (Customer, Owner, General Contractor, Lender) within thirty (30) days following the first delivery of labor, services or materials to the property, either by e-mail with a confirmed receipt, registered or certified mail, or statutory overnight delivery.

TRADITION LIEN SERVICE can research and send this notice on your behalf for only $27. Or, you can print this MISSISSIPPI notice and others by purchasing PreLien2Lien from TRADITION SOFTWARE for as little as $164.

On New Residential projects MISSISSIPPI Code Mississippi Code § 85-7-407 (2) requires a Preliminary Notice must be served to all legal parties on a project (Customer, Owner, General Contractor, Lender) within thirty (30) days following the first delivery of labor, services or materials to the property, either by e-mail with a confirmed receipt, registered or certified mail, or statutory overnight delivery.

TRADITION LIEN SERVICE can research and send this notice on your behalf for only $27. Or, you can print this MISSISSIPPI notice and others by purchasing PreLien2Lien from TRADITION SOFTWARE for as little as $164.


LIEN WARNING
Commercial Existing Residential New Residential
Notice Of Intent To File A Bond Claim, Claim Of Lien Or Stop Notice Pre-Lien Notice To Owner Pre-Lien Notice To Owner

Optional. Use a Notice Of Intent to notify all legal parties (Owner, Lender, Customer, Lender/Surety) for a Private project that a Bond Claim, Claim Of Lien or Stop Notice will be filed if payment is not received by a stated deadline, usually ten (10) days.

TRADITION LIEN SERVICE can research and and send this notice on your behalf for only $55. Or, you can print this MISSISSIPPI notice and others by purchasing PreLien2Lien from TRADITION SOFTWARE for as little as $164.

MISSISSIPPI Code § 85-7-409 (3) requires on single family construction a Pre-Lien Notice To Owner be sent by a lien claimant to the Owner ten (10) days in advance of recording a MISSISSIPPI Claim Of Lien.

TRADITION LIEN SERVICE can research and and send this notice on your behalf for only $55. Or, you can print this MISSISSIPPI notice and others by purchasing PreLien2Lien from TRADITION SOFTWARE for as little as $164.

MISSISSIPPI Code § 85-7-409 (3) requires on single family construction a Pre-Lien Notice To Owner be sent by a lien claimant to the Owner ten (10) days in advance of recording a MISSISSIPPI Claim Of Lien.

TRADITION LIEN SERVICES can research and and send this notice on your behalf for only $55. Or, you can print this MISSISSIPPI notice and others by purchasing PreLien2Lien from TRADITION SOFTWARE for as little as $164.


CONSTRUCTION LIEN
Commercial Existing Residential New Residential
Claim Of Lien Claim Of Lien Claim Of Lien

On private Commercial projects MISSISSIPPI Code Annotated § 85-7-409 mandates that a Claim Of Lien can be filed only by the Prime/General Contractor or Subcontractor. It should be recorded with the Chancery Clerk in the county in which the project is located. I It must be recorded no later than ninety (90) days after the last day of providing equipment, labor, materials or services for the improvement of a project. A recorded copy of the Claim should then be promptly mailed by certified mail or personally delivered to the improved property’s Owner, Agent or Trustee along with other legal parties for the project (Lender/Surety).

A lawsuit (Payment Action) must be filed within 180 days from the date of the recording of the lien.

TRADITION LIEN SERVICE can research, prepare and record this notice on your behalf for only $175. Or, you can print this MISSISSIPPI notice and others by purchasing PreLien2Lien from TRADITION SOFTWARE for as little as $164.

On private Existing Residential projects MISSISSIPPI Code Annotated § 85-7-409 mandates that a Claim Of Lien can be filed only by the Prime/General Contractor or Subcontractor. It should be recorded with the Chancery Clerk in the county in which the project is located. It must be recorded no later than ninety (90) days after the last day of providing equipment, labor, materials or services for the improvement of a project. A recorded copy of the Claim should then be promptly mailed by certified mail or personally delivered to the improved property’s Owner, Agent or Trustee along with other legal parties for the project (Lender/Surety).

A lawsuit (Payment Action) must be filed within 180 days from the date of the recording of the lien.

TRADITION LIEN SERVICE can research, prepare and record this notice on your behalf for only $175. Or, you can print this MISSISSIPPI notice and others by purchasing PreLien2Lien from TRADITION SOFTWARE for as little as $164.

On private New Residential projects MISSISSIPPI Code Annotated § 85-7-409 mandates that a Claim Of Lien can be filed only by the Prime/General Contractor or Subcontractor. It should be recorded with the Chancery Clerk in the county in which the project is located. It must be recorded no later than ninety (90) days after the last day of providing equipment, labor, materials or services for the improvement of a project. A recorded copy of the Claim should then be promptly mailed by certified mail or personally delivered to the improved property’s Owner, Agent or Trustee along with other legal parties for the project (Lender/Surety).

A lawsuit (Payment Action) must be filed within 180 days from the date of the recording of the lien.

TRADITION LIEN SERVICE can research, prepare and record this notice on your behalf for only $175. Or, you can print this MISSISSIPPI notice and others by purchasing PreLien2Lien from TRADITION SOFTWARE for as little as $164.