Skip to main content
Lien Deadlines And Notices
DISCLAIMER: TRADITION LIEN SERVICE, a Division of Tradition Software, Inc. makes no warrant, express or implied for the use of this website. In no event shall TRADITION LIEN SERVICE be liable to anyone for any problem, claim or loss arising out of the use of TraditionLienService.com. TRADITION LIEN SERVICE is not engaged in practicing law nor does TRADITION LIEN SERVICE provide legal advice in the state of Montana.

1ST NOTICE
Commercial Existing Residential New Residential
Notice Of The Right To Claim A Lien Notice Of The Right To Claim A Lien Notice Of The Right To Claim A Lien

On private Commercial projects Subcontractors have up to twenty (20) days to deliver by certified mail or personal delivery a MONTANTA Notice Of The Right To Claim A Lien to the Owner and other legal parties on a project after first furnishing equipment, materials, labor or services.

TRADITION LIEN SERVICE can research and send this notice on your behalf for only $27. Or, you can print this MONTANA notice and others by purchasing PreLien2Lien from TRADITION SOFTWARE for as little as $164.

On private Existing Residential projects Subcontractors have up to twenty (20) days to deliver by certified mail or personal delivery a MONTANTA Notice Of The Right To Claim A Lien to the Owner and other legal parties on a project after first furnishing equipment, materials, labor or services.

TRADITION LIEN SERVICE can research and send this notice on your behalf for only $27. Or, you can print this MONTANA notice and others by purchasing PreLien2Lien from TRADITION SOFTWARE for as little as $164.

On private New Residential projects Subcontractors have up to twenty (20) days to deliver by certified mail or personal delivery a MONTANTA Notice Of The Right To Claim A Lien to the Owner and other legal parties on a project after first furnishing equipment, materials, labor or services.

TRADITION LIEN SERVICE can research and send this notice on your behalf for only $27. Or, you can print this MONTANA notice and others by purchasing PreLien2Lien from TRADITION SOFTWARE for as little as $164.


LIEN WARNING
Commercial Existing Residential New Residential
Notice Of Intent To File A Bond Claim, Construction Lien Or Stop Notice Notice Of Intent To File A Bond Claim, Construction Lien Or Stop Notice Notice Of Intent To File A Bond Claim, Construction Lien Or Stop Notice

Optional. Consider delivering by certified mail a Notice Of Intent To File A Bond Claim, Construction Lien or Stop Notice to the Owner and other legal parties ten (10) days before recording a lien.

TRADITION LIEN SERVICE can research and and send this notice on your behalf for only $55. Or, you can print this MONTANA notice and others by purchasing PreLien2Lien from TRADITION SOFTWARE for as little as $164.

Optional. Consider delivering by certified mail a Notice Of Intent To File A Bond Claim, Construction Lien or Stop Notice to the Owner and other legal parties ten (10) days before recording a lien.

TRADITION LIEN SERVICE can research and and send this notice on your behalf for only $55. Or, you can print this MONTANA notice and others by purchasing PreLien2Lien from TRADITION SOFTWARE for as little as $164.

Optional. Consider delivering by certified mail a Notice Of Intent To File A Bond Claim, Construction Lien or Stop Notice to the Owner and other legal parties ten (10) days before recording a lien.

TRADITION LIEN SERVICE can research and and send this notice on your behalf for only $55. Or, you can print this MONTANA notice and others by purchasing PreLien2Lien from TRADITION SOFTWARE for as little as $164.


CONSTRUCTION LIEN
Commercial Existing Residential New Residential
Construction Lien Construction Lien Construction Lien

On private Commercial projects General/Prime contractors and Subcontractors can record a MONTANA Construction Lien up to ninety (90) days after the last day providing equipment, labor, materials or services for a project. Record at the county Recorder’s Office in the County where the project was located.

Claimants are required to file suit to foreclose on a MONTANA Construction Lien within two (2) years from the date the MONTANA Construction Lien was recorded.

TRADITION LIEN SERVICE can research, prepare and record this notice on your behalf for only $175. Or, you can print this MONTANA notice and others by purchasing PreLien2Lien from TRADITION SOFTWARE for as little as $164.

On private Existing Residential projects General/Prime contractors and Subcontractors can record a MONTANA Construction Lien up to ninety (90) days after the last day providing equipment, labor, materials or services for a project. Record at the county Recorder’s Office in the County where the project was located.

Claimants are required to file suit to foreclose on a MONTANA Construction Lien within two (2) years from the date the MONTANA Construction Lien was recorded.

TRADITION LIEN SERVICE can research, prepare and record this notice on your behalf for only $175. Or, you can print this MONTANA notice and others by purchasing PreLien2Lien from TRADITION SOFTWARE for as little as $164.

On private New Residential projects General/Prime contractors and Subcontractors can record a MONTANA Construction Lien up to ninety (90) days after the last day providing equipment, labor, materials or services for a project. Record at the county Recorder’s Office in the County where the project was located.

Claimants are required to file suit to foreclose on a MONTANA Construction Lien within two (2) years from the date the MONTANA Construction Lien was recorded.

TRADITION LIEN SERVICE can research, prepare and record this notice on your behalf for only $175. Or, you can print this MONTANA notice and others by purchasing PreLien2Lien from TRADITION SOFTWARE for as little as $164.