Lien Deadlines And Notices | DISCLAIMER: TRADITION LIEN SERVICE, a Division of Tradition Software, Inc. makes no warrant, express or implied for the use of this website. In no event shall TRADITION LIEN SERVICE be liable to anyone for any problem, claim or loss arising out of the use of TraditionLienService.com. TRADITION LIEN SERVICE is not engaged in practicing law nor does TRADITION LIEN SERVICE provide legal advice in the state of Utah. |
1ST NOTICE | ||
Commercial | Existing Residential | New Residential |
Notice Of Commencement | Preliminary Notice | Notice Of Commencement | Preliminary Notice | Notice Of Commencement | Preliminary Notice |
On private Commercial projects General/Prime Contractors must file a UTAH Notice Of Commencement with the UTAH State Construction Registry (www.utah.gov/cnr/) no later than fifteen (15) days after either a building permit is issued or no later than fifteen (15) days after the commencement of start of a construction related improvement. |
On private Existing Residential projects General/Prime Contractors must file a UTAH Notice Of Commencement with the UTAH State Construction Registry (www.utah.gov/cnr/) no later than fifteen (15) days after either a building permit is issued or no later than fifteen (15) days after the commencement of start of a construction related improvement. |
On private New Residential projects General/Prime Contractors must file a UTAH Notice Of Commencement with the UTAH State Construction Registry (www.utah.gov/cnr/) no later than fifteen (15) days after either a building permit is issued or no later than fifteen (15) days after the commencement of start of a construction related improvement. |
| ||
LIEN WARNING | ||
Commercial | Existing Residential | New Residential |
N/A | N/A | N/A |
N/A | N/A | N/A |
| ||
CONSTRUCTION LIEN | ||
Commercial | Existing Residential | New Residential |
Notice Of Lien | Notice Of Lien | Notice Of Lien |
On private Commercial projects General/Prime contractors and Subcontractors must record a notarized UTAH Notice of Lien no later than ninety (90) days from the date a UTAH Notice of Completion is filed with the UTAH State Construction Registry (www.utah.gov/cnr/) OR one hundred eighty (180) days from the last day providing equipment, labor, materials or services for a construction related improvement. |
On private Existing Residential projects General/Prime contractors and Subcontractors must record a notarized UTAH Notice of Lien no later than ninety (90) days from the date a UTAH Notice of Completion is filed with the UTAH State Construction Registry (www.utah.gov/cnr/) OR one hundred eighty (180) days from the last day providing equipment, labor, materials or services for a construction related improvement. |
On private New Residential projects General/Prime contractors and Subcontractors must record a notarized UTAH Notice of Lien no later than ninety (90) days from the date a UTAH Notice of Completion is filed with the UTAH State Construction Registry (www.utah.gov/cnr/) OR one hundred eighty (180) days from the last day providing equipment, labor, materials or services for a construction related improvement. |
|