Lien Deadlines And Notices
DISCLAIMER: TRADITION LIEN SERVICE, a Division of Tradition Software, Inc. makes no warrant, express or implied for the use of this website. In no event shall TRADITION LIEN SERVICE be liable to anyone for any problem, claim or loss arising out of the use of TraditionLienService.com. TRADITION LIEN SERVICE is not engaged in practicing law nor does TRADITION LIEN SERVICE provide legal advice in the state of Wyoming.

1ST NOTICE
Commercial Existing Residential New Residential
Notice Of Right To Lien Notice Of Right To Lien Notice Of Right To Lien

On private Commercial projects WYOMING Statutes § 29-2-112 mandate that a WYOMING Notice Of Right To Lien must be served by the General/Prime Contractor or Subcontractor to the Owner within thirty (30) days after first furnishing construction related labor, professional services, materials, machinery, fixtures or tools to a jobsite. If you are a Subcontractor it is also recommended that you send a copy of the WYOMING Notice To Owner to the other legal parties on a jobsite (Customer, Prime/General Contractor, Lender).

TRADITION LIEN SERVICE can research and send this notice on your behalf for only $28. Or, you can print this WYOMING notice and others by purchasing PreLien2Lien from TRADITION SOFTWARE for as little as $164.

On private Existing Residential projects WYOMING Statutes § 29-2-112 mandate that a WYOMING Notice Of Right To Lien must be served by the General/Prime Contractor or Subcontractor to the Owner within thirty (30) days after first furnishing construction related labor, professional services, materials, machinery, fixtures or tools to a jobsite. If you are a Subcontractor it is also recommended that you send a copy of the WYOMING Notice To Owner to the other legal parties on a jobsite (Customer, Prime/General Contractor, Lender).

TRADITION LIEN SERVICE can research and send this notice on your behalf for only $28. Or, you can print this WYOMING notice and others by purchasing PreLien2Lien from TRADITION SOFTWARE for as little as $164.

On private New Residential projects WYOMING Statutes § 29-2-112 mandate that a WYOMING Notice Of Right To Lien must be served by the General/Prime Contractor or Subcontractor to the Owner within thirty (30) days after first furnishing construction related labor, professional services, materials, machinery, fixtures or tools to a jobsite. If you are a Subcontractor it is also recommended that you send a copy of the WYOMING Notice To Owner to the other legal parties on a jobsite (Customer, Prime/General Contractor, Lender).

TRADITION LIEN SERVICE can research and send this notice on your behalf for only $28. Or, you can print this WYOMING notice and others by purchasing PreLien2Lien from TRADITION SOFTWARE for as little as $164.


LIEN WARNING
Commercial Existing Residential New Residential
Notice Of Intention To File A Lien Notice Of Intention To File A Lien Notice Of Intention To File A Lien

On private Commercial projects WYOMING Statutes § 29-2-107 mandate that a General/Prime Contractor or Subcontractor deliver by certified mail or personal delivery to the Owner a WYOMING Notice Of Intention To File A Lien twenty (20) days prior to filing a notarized WYOMING Lien Statement. It is also recommended that you deliver by certified mail or personal delivery a copy of the WYOMING Notice Of Intention To File A Lien to the other legal parties for a jobsite (Customer, Prime/General Contractor, Lender).

TRADITION LIEN SERVICE can research and and send this notice on your behalf for only $55. Or, you can print this WYOMING notice and others by purchasing PreLien2Lien from TRADITION SOFTWARE for as little as $164.

On private Existing Residential projects WYOMING Statutes § 29-2-107 mandate that a General/Prime Contractor or Subcontractor deliver by certified mail or personal delivery to the Owner a WYOMING Notice Of Intention To File A Lien twenty (20) days prior to filing a notarized WYOMING Lien Statement. It is also recommended that you deliver by certified mail or personal delivery a copy of the WYOMING Notice Of Intention To File A Lien to the other legal parties for a jobsite (Customer, Prime/General Contractor, Lender).

TRADITION LIEN SERVICE can research and and send this notice on your behalf for only $55. Or, you can print this WYOMING notice and others by purchasing PreLien2Lien from TRADITION SOFTWARE for as little as $164.

On private New Residential projects WYOMING Statutes § 29-2-107 mandate that a General/Prime Contractor or Subcontractor deliver by certified mail or personal delivery to the Owner a WYOMING Notice Of Intention To File A Lien twenty (20) days prior to filing a notarized WYOMING Lien Statement. It is also recommended that you deliver by certified mail or personal delivery a copy of the WYOMING Notice Of Intention To File A Lien to the other legal parties for a jobsite (Customer, Prime/General Contractor, Lender).

TRADITION LIEN SERVICE can research and and send this notice on your behalf for only $55. Or, you can print this WYOMING notice and others by purchasing PreLien2Lien from TRADITION SOFTWARE for as little as $164.


CONSTRUCTION LIEN
Commercial Existing Residential New Residential
Lien Statement Lien Statement Lien Statement

On private Commercial projects WYOMING Statutes §§ 29-1-301; 29-2-106) mandate that General/Prime contractors have one hundred twenty (120) days and Subcontractors have ninety (90) days to record a notarized WYOMING Lien Statement at the County Clerk’s office in the county where the project occurred after the last day equipment, labor materials or services were provided at a jobsite. All legal parties must be notified by certified mail or personal delivery of the recorded WYOMING Lien Statement.

A WYOMING Lien Statement must be perfected through a foreclosure action at the Superior Court in the county where the project is located within one hundred eighty (180) days of the WYOMING Lien Statement being recorded.

TRADITION LIEN SERVICE can research, prepare and record this notice on your behalf for only $175. Or, you can print this WYOMING notice and others by purchasing PreLien2Lien from TRADITION SOFTWARE for as little as $164.

On private Existing Residential projects WYOMING Statutes §§ 29-1-301; 29-2-106) mandate that General/Prime contractors have one hundred twenty (120) days and Subcontractors have ninety (90) days to record a notarized WYOMING Lien Statement at the County Clerk’s office in the county where the project occurred after the last day equipment, labor materials or services were provided at a jobsite. All legal parties must be notified by certified mail or personal delivery of the recorded WYOMING Lien Statement.

A WYOMING Lien Statement must be perfected through a foreclosure action at the Superior Court in the county where the project is located within one hundred eighty (180) days of the WYOMING Lien Statement being recorded.

TRADITION LIEN SERVICE can research, prepare and record this notice on your behalf for only $175. Or, you can print this WYOMING notice and others by purchasing PreLien2Lien from TRADITION SOFTWARE for as little as $164.

On private New Residential projects WYOMING Statutes §§ 29-1-301; 29-2-106) mandate that General/Prime contractors have one hundred twenty (120) days and Subcontractors have ninety (90) days to record a notarized WYOMING Lien Statement at the County Clerk’s office in the county where the project occurred after the last day equipment, labor materials or services were provided at a jobsite. All legal parties must be notified by certified mail or personal delivery of the recorded WYOMING Lien Statement.

A WYOMING Lien Statement must be perfected through a foreclosure action at the Superior Court in the county where the project is located within one hundred eighty (180) days of the WYOMING Lien Statement being recorded.

TRADITION LIEN SERVICE can research, prepare and record this notice on your behalf for only $175. Or, you can print this WYOMING notice and others by purchasing PreLien2Lien from TRADITION SOFTWARE for as little as $164.