DISCLAIMER: TRADITION LIEN SERVICE, a Division of Tradition Software, Inc. makes no warrant, express or implied for the use of this website. In no event shall TRADITION LIEN SERVICE be liable to anyone for any problem, claim or loss arising out of the use of TraditionLienService.com. TRADITION LIEN SERVICE is not engaged in practicing law nor does TRADITION LIEN SERVICE provide legal advice in the state of Michigan.
10 Simple Mechanic’s Lien Rules for Contractors and Subcontractors
Doing Construction Business in the State of Michigan

Prepared by: Craig R. Altman – President, TRADITION SOFTWARE, INC.

1. An Owner must file a Notice of Commencement prior to the start of a project. This must be filed with the Local Registrar of Deeds in the county where the project is located. It must contain a description of the property and the names and addresses of the legal parties on the project (Customer, Owner, General Contractor and Lender).

2. A General/Prime Contractor does not have to file a Notice of Furnishing if they have a direct contract with the Owner.

3. A Subcontractor who does not have a direct contract with the owner must file an Notice of Furnishing within 20 days after the first day of furnishing construction related labor, professional services, materials, machinery, fixtures or tools to a jobsite. It should be served to all legal parties on a project (Customer, Owner, General Contractor and Lender). It must be delivered in person or by certified mail to the owner of the property along with any other legal parties related to the improvement of the property (Customer, Owner, General Contractor and Lender).

4. You have 90 days to file a Claim of Lien (Mechanic’s Lien) with the in the county where the project occurred after the last day labor was provided at a jobsite or materials were delivered. All legal parties must be notified by Certified Mail or personal delivery of the Claim of Lien within 15 days of it being filed. Warranty work may not be liened in a Claim of Lien.

5. A Claim Of Lien (Mechanic’s Lien) cannot be filed for projects that are City, County, State or Federal related.

6. A Claim of Lien must be perfected within one year of the Claim of Lien being recorded through a foreclosure action. Concurrent with the foreclosure filing, a Notice of Lis Pendens must be filed with the Registrar of Deeds documenting that legal action has been initiated against the property. A Claim Of Lien is automatically discharged if it is not perfected within one year.

7. Legal expenses are not lienable on a Claim of Lien.

8. General/Prime contractors cannot enforce a No-Lien contract on a subcontractor prior to the entering of a contract or doing work.

9. If a Claim of Lien balance is paid in full by the Owner or another legal party, you must file a Discharge of Construction Lien. Additionally, if a Notice of Lis Pendens was filed, a Release of Lis Pendens must subsequently be filed upon receiving payment.

10. Unlicensed Residential Homebuilders are not eligible for Mechanic’s Lien rights.

CONSTRUCTION LIEN ACT

ACT 497 of 1980

AN ACT to establish, protect, and enforce by lien the rights of persons performing labor or providing material or equipment for the improvement of real property; to provide for certain defenses with respect thereto; to establish a homeowner construction lien recovery fund within the department of licensing and regulation; to provide for the powers and duties of certain state officers; to provide for the assessments of certain occupations; to prescribe penalties; and to repeal certain acts and parts of acts.

PART 1

570.1101 Short Title

570.1102 Definitions

570.1103 Definitions

570.1104 Definitions

570.1105 Definitions

570.1106 Definitions

570.1107 Persons Entitled to Construction Liens, Interests Affected, Vendee or Lessee, Joint Ownership, Limitation of Amount of Liens

570.1108 Notice of Commencement, Service, Posting, Exemption

570.1108a Notice of Commencement, Residential Structure, Service, Posting

570.1109 Notice of Furnishing, Service

570.1110 Sworn Statement by Contractor, Subcontractor, Owner May Withhold Payment, Direct Payment, Notice to General Contractor, Failure to Provide Sworn Statement, Penalties

570.1111 Claim of Lien, Recording, Time

570.1112 Recording, Indexing, Fees

570.1113 Inspection and Copying of Contract, Statement of Amount Unpaid, Statement of Labor and Material Furnished and Amount Unpaid

570.1114 Contractors License, Notice in Contract

570.1115 Advance Waiver Prohibited, Waivers of Lien, Partial Waivers, Conditional Waivers, Retainage, Waiver Forms

570.1116 Release Bond, Notice, Objection to Surety

570.1117 Foreclosure Proceedings, Limitations, Notice of Lis Pendens, Parties, Personal Action

570.1118 Foreclosure Action, Venue, Trial, Attorneys Fees

570.1119 Priorities, Advances from Construction Loans, Retainage

570.1120 Part Performance

570.1121 Judgment, Sale, Redemption, Deficiency Judgment

570.1122 Receiver

570.1123 Completion of Construction or Sale or by Receiver

570.1124 Final Account of Receiver

570.1125 Liens Assignable

570.1126 Limitations on Condominium Liens

570.1127 Discharge of Lien

570.1128 Certificate That No Foreclosure Proceedings Have Been Commenced

PART 2

570.1201 Homeowner Construction Lien Recovery Fund, Fees

570.1202 Management, Audit

570.1203 Homeowner Affidavit, Recovery from the Fund, Defense by Attorney General

570.1204 Payments from the Fund

570.1205 Immunity, Recoupment

570.1206 Disciplinary Proceedings

570.1207 False Information, Felony

PART 3

570.1301 Residential Structures, Application of Act, Statement of Date of Contract, Notice of Furnishing, Definitions

570.1302 Liberal Construction

570.1304 Joint Review Committee

570.1305 Effective Date

MICHIGAN COMPILED LAWS

CHAPTER 570 LIENS

CONSTRUCTION LIEN ACT

PART 1

570.1101 Short Title

Sec. 101. This act shall be known and may be cited as the “construction lien act”.

570.1102 Definitions

Sec. 102. For the purposes of this act, the words and phrases defined in sections 103 to 106 have the meanings ascribed to them in those sections.

570.1103 Definitions

Sec. 103. (1) “Actual physical improvement” means the actual physical change in, or alteration of, real property as a result of labor provided, pursuant to a contract, by a contractor, subcontractor, or laborer which is readily visible and of a kind that would alert a person upon reasonable inspection of the existence of an improvement. Actual physical improvement does not include that labor which is provided in preparation for that change or alteration, such as surveying, soil boring and testing, architectural or engineering planning, or the preparation of other plans or drawings of any kind or nature. Actual physical improvement does not include supplies delivered to or stored at the real property.

(2) “Co-lessee” a person having an interest in real property, the nature of which is identical to that of the interest of the lessee who contracted for the improvement to the real property, whether the extent of such interest is identical or not.

(3) “Construction lien” means the lien of a contractor, subcontractor, supplier, or laborer, as described in section 107.

(4) “Contract” means a contract, of whatever nature, for the providing of improvements to real property, including any and all additions to, deletions from, and amendments to the contract.

(5) “Contractor” means a person who, pursuant to a contract with the owner or lessee of real property, provides an improvement to real property.

(6) “Co-owner” means a person having an interest in real property, the nature of which is identical to that of the interest of the owner who contracted for the improvement to the real property, whether the extent of such interest is identical or not.

570.1104 Definitions

Sec. 104. (1) “Court” means the circuit court in which an action to enforce a construction lien through foreclosure is pending.

(2) “Department” means the department of licensing and regulation.

(3) “Designee” means the person named by an owner or lessee to receive, on behalf of the owner or lessee, all notices or other instruments whose furnishing is required by this act. The owner or lessee may name himself or herself as designee. The owner or lessee may not name the contractor as designee. However, a contractor who is providing only architectural or engineering services may be named as designee.

(4) “Fringe benefits and withholdings” means compensation due an employee pursuant to a written contract or written policy for holiday, time off for sickness or injury, time off for personal reasons or vacation, bonuses, authorized expenses incurred during the course of employment, and any other contributions made to or on behalf of an employee.

(5) “Fund” means the homeowner construction lien recovery fund created under part 2.

(6) “General contractor” means a contractor who contracts with an owner or lessee to provide, directly or indirectly through contracts with subcontractors, suppliers, or laborers, substantially all of the improvements to the property described in the notice of commencement.

(7) “Improvement” means the result of labor or material provided by a contractor, subcontractor, supplier, or laborer, including, but not limited to, surveying, engineering and architectural planning, construction management, clearing, demolishing, excavating, filling, building, erecting, constructing, altering, repairing, ornamenting, landscaping, paving, leasing equipment, or installing or affixing a fixture or material, pursuant to a contract.

(8) “Laborer” means an individual who, pursuant to a contract with a contractor or subcontractor, provides an improvement to real property through the individual’s personal labor.

570.1105 Definitions

Sec. 105. (1) “Lessee” means a person, other than the owner, who holds an interest, other than a security interest, in real property.

(2) “Lien claimant” means a person having a right to a construction lien under this act.

(3) “Owner” means a person holding a fee interest in real property or an equitable interest arising out of a land contract.

570.1106 Definitions

Sec. 106. (1) “Person” means an individual, corporation, partnership, sole proprietorship, association, other legal entity, or any combination thereof.

(2) “Project” means the aggregate of improvements contracted for by the contracting owner.

(3) “Residential structure” means an individual residential condominium unit or a residential building containing not more than 2 residential units, the land on which it is or will be located, and all appurtenances thereto, in which the owner or lessee contracting for the improvement is residing or will reside upon completion of the improvement.

(4) “Subcontractor” means a person, other than a laborer or supplier, who pursuant to a contract between himself or herself and a person other than the owner or lessee performs any part of a contractor’s contract for an improvement.

(5) “Supplier” means a person who, pursuant to a contract with a contractor or a subcontractor, leases, rents, or in any other manner provides material or equipment which is used in the improvement of real property.

(6) “Wages” means all earnings of an employee whether determined on the basis of time, task, piece, commission, or other method of calculation for labor or services except those defined as fringe benefits and withholdings.

570.1107 Persons Entitled to Construction Liens, Interests Affected, Vendee or Lessee, Joint Ownership, Limitation of Amount of Liens

Sec. 107. (1) Each contractor, subcontractor, supplier, or laborer who provides an improvement to real property shall have a construction lien upon the interest of the owner or lessee who contracted for the improvement to the real property, as described in the notice of commencement provided for by section 108 or 108a, the interest of an owner who has subordinated his or her interest to the mortgage for the improvement of the real property, and the interest of an owner who has required the improvement. A construction lien acquired pursuant to this act shall not exceed the amount of the lien claimant’s contract less payments made on the contract.

(2) A construction lien under this act shall attach to the entire interest of the owner or lessee who contracted for the improvement, including any subsequently acquired legal or equitable interest.

(3) Each contractor, subcontractor, supplier, or laborer who provides an improvement to real property to which the person contracting for the improvement had no legal title shall have a construction lien upon the improvement for which the contractor, subcontractor, supplier, or laborer provided labor, material, or equipment. The forfeiture, surrender, or termination of any title or interest held by any owner or lessee who contracted for an improvement to the property or by any owner who subordinated his or her interest to the mortgage for the improvement, or by any owner who has required the improvement shall not defeat the lien of the contractor, subcontractor, supplier, or laborer upon the improvement.

(4) If the rights of a person contracting for an improvement as a land contract vendee or a lessee are forfeited, surrendered, or otherwise terminated, any lien claimant who has provided a notice of furnishing or is excused from providing a notice of furnishing pursuant to section 108, 108a, or 109 and who performs the covenants contained in the land contract or lease within 30 days after receiving actual notice of the forfeiture, surrender, or termination shall be subrogated to the rights of the contracting vendee or lessee as those rights existed immediately before the forfeiture, surrender, or termination.

(5) For purposes of this act, if the real property is owned or leased by more than 1 person, an improvement to real property pursuant to a contract which was entered into by an owner or lessee shall be presumed to have been consented to by any other co-owner or co-lessee, but the presumption shall in all cases be rebuttable. If enforcement of a construction lien through foreclosure is sought and the court finds that the improvement has been consented to by a co-owner or co-lessee who did not contract for the improvement, the court shall order the entire interest of that co-owner or co-lessee, including any subsequently acquired legal or equitable interest, to be subject to the construction lien. A deficiency judgment shall not be entered against a noncontracting owner, co-owner, lessee, or co-lessee.

(6) If the real property of an owner or lessee is subject to construction liens, the sum of the construction liens shall not exceed the amount which the owner or lessee agreed to pay the person with whom he or she contracted for the improvement as modified by any and all additions, deletions, and any other amendments, less payments made by or on behalf of the owner or lessee, pursuant to either a contractor’s sworn statement or a waiver of lien, in accordance with this act.

570.1108 Notice of Commencement, Service, Posting, Exemption

Sec. 108. (1) Before the commencement of any actual physical improvements to real property, the owner or lessee contracting for the improvements shall record in the office of the register of deeds for each county in which the real property to be improved is located a notice of commencement, in the form set forth in this section. If all improvements relate to a single project only 1 notice of commencement need be recorded. A subsequent notice of commencement need not be recorded for an improvement to any real property which currently has a notice of commencement recorded in the office of the register of deeds if that recorded notice of commencement contains the same information as the subsequent notice of commencement.

(2) The notice of commencement shall contain the following information:

(a) The legal description of the real property on which the improvement is to be made. A description conforming to section 212 or 255 of Act No. 288 of the Public Acts of 1967, being sections 560.212 and 560.255 of the Michigan Compiled Laws, shall be a sufficient legal description.

(b) The name, address, and capacity of the owner or lessee of the real property contracting for the improvement.

(c) The name and address of the fee owner of the real property, if the person contracting for the improvement is a land contract vendee or lessee.

(d) The name and address of the owner’s or lessee’s designee.

(e) The name and address of the general contractor, if any.

(f) The following statement:

“To lien claimants and subsequent purchasers:

Take notice that work is about to commence on an improvement to the real property described in this instrument. A person having a construction lien may preserve the lien by providing a notice of furnishing to the above named designee and the general contractor, if any, and by timely recording a claim of lien, in accordance with law. A person having a construction lien arising by virtue of work performed on this improvement should refer to the name of the owner or lessee and the legal description appearing in this notice. A person subsequently acquiring an interest in the land described is not required to be named in a claim of lien. A copy of this notice with an attached form for notice of furnishing may be obtained upon making a written request by certified mail to the above named owner or lessee; the designee; or the person with whom you have contracted.”

(g) The name and address of the person preparing the notice.

(h) An affidavit of the owner or lessee or the agent of the owner or lessee which verifies the notice.

(3) Each copy of the notice of commencement shall have a blank notice of furnishing as described in section 109 attached to it. The blank notice of furnishing shall be easily detachable from the copy of the notice and need not be recorded.

(4) Incorrect information contained in the notice of commencement furnished by or for an owner or lessee shall not affect adversely the rights of a lien claimants as against the property of that owner or lessee.

(5) The owner, lessee, or designee, within 10 days after the date of mailing of a written request by certified mail from a subcontractor, supplier, or laborer, shall provide a copy of the notice of commencement, together with an attached blank notice of furnishing form, to the subcontractor, supplier, or laborer requesting a copy of the notice of commencement.

(6) A contractor who has been provided with a notice of commencement from the owner, lessee, or designee, within 10 days after the date of mailing of a written request by certified mail from a subcontractor, supplier, or laborer who has a direct contract with the contractor, shall provide a copy of the notice of commencement, together with an attached blank notice of furnishing form, to the subcontractor, supplier, or laborer requesting a copy of the notice of commencement.

(7) A subcontractor who has been provided with a notice of commencement from the owner, lessee, designee, contractor, or subcontractor, within 10 days after the date of mailing of a written request by certified mail from a subcontractor, supplier, or laborer who has a direct contract with the subcontractor, shall provide a copy of the notice of commencement, together with an attached blank notice of furnishing form, to the subcontractor, supplier, or laborer requesting a copy of the notice of commencement.

(8) The owner, lessee, or designee shall post and keep posted a copy of the notice of commencement in a conspicuous place on the real property described in the notice during the course of the actual physical improvement to the real property.

(9) The owner, lessee, or designee shall provide a copy of the notice of commencement to the general contractor, if any. Failure of the owner, lessee, or designee to provide the notice of commencement to the general contractor shall render the owner or lessee liable to the general contractor for all actual expenses sustained by the general contractor in obtaining the information otherwise provided by the notice of commencement.

(10) Failure of the owner, lessee, or designee to record the notice of commencement, in accordance with this section, shall operate to extend the time Within which a subcontractor or supplier may provide a notice of furnishing, as described in section 109, until 20 days after the notice of commencement has been recorded.

(11) Failure of the owner, lessee, or designee to provide, upon written request, the notice of commencement, in accordance with this section, shall operate to extend the time within which a subcontractor or supplier may provide a notice of furnishing, as described in section 109, until 20 days after the notice of commencement actually has been furnished to the subcontractor or supplier.

(12) Failure of the owner, lessee, or designee to record the notice of commencement, in accordance with this section, shall operate to extend the time within which a laborer may provide a notice of furnishing, as described in section 109, until 30 days after the notice of commencement has been recorded, or until the time in which to provide the notice of furnishing in accordance with section 109 expires, whichever is later.

(13) Failure of the owner, lessee, or designee to provide the notice of commencement, in accordance with this section, shall operate to extend the time within which a laborer may provide a notice of furnishing, as described in section 109, until 30 days after the notice of commencement has been provided, or until the time in which to provide the notice of furnishing in accordance with section 109 expires, whichever is later.

(14) Failure of the owner, lessee, or designee to post or keep posted a copy of the notice of commencement as provided in subsection (8) shall render the owner or lessee liable to a subcontractor, supplier, or laborer who becomes a lien claimant for all actual expenses sustained by the lien claimant in obtaining the information otherwise provided by the posting.

(15) Failure of a contractor, who has been provided with a notice of commencement from the owner, lessee, or designee, to provide the notice of commencement upon the request of a lien claimant who has a direct contract with the contractor for an improvement to property shall render the contractor liable to the lien claimant for all actual expenses sustained by the lien claimant in obtaining the information otherwise provided by the notice of commencement.

(16) Failure of a subcontractor, who has been provided with a notice of commencement from the owner, lessee, designee, contractor, or subcontractor to provide the notice of commencement upon the request of a subcontractor, supplier, or laborer who has a direct contract with the subcontractor shall render the subcontractor liable to such subcontractor, supplier, or laborer for all actual expenses sustained by the subcontractor, supplier, or laborer in obtaining the information otherwise provided by the notice of commencement.

(17) If the owner, lessee, or designee fails to provide, record, and post the notice of commencement as provided in this act and if, after the first actual physical improvement, the contractor by certified mail makes a written request to the owner, lessee, or designee to provide, record, and post the notice of commencement and the owner, lessee, or designee fails within 10 days after receipt of the request to do so, the owner or lessee shall be barred from requiring the contractor to hold the owner or lessee harmless from liens of lien claimants to the extent such lien claims could have otherwise been avoided through proper payment, had such request been complied with. If the contractor pays a valid lien claim at the direction of the owner, lessee, or designee after the owner, lessee, or designee has failed to comply with this section, the owner or lessee shall be liable to the contractor to the extent the lien claim could have otherwise been avoided through proper payment had such request been complied with. This subsection shall not apply if the lien claimant appears on a sworn statement provided to the contractor and the claim of the lien claimant appearing on the sworn statement could have been avoided had payment been made in accordance with the sworn statement.

(18) This section shall not apply to an improvement to a residential structure.

570.1108a Notice of Commencement, Residential Structure, Service, Posting

Sec. 108a. (1) An owner or lessee contracting for an improvement to a residential structure shall prepare and provide a notice of commencement to a contractor, subcontractor, supplier, or laborer who has made a written request for the notice pursuant to this section.

(2) The notice of commencement shall contain the following information:

(a) The legal description of the real property on which the improvement is to be made. A description conforming to section 212 or 255 of Act No. 288 of the Public Acts of 1967, being sections 560.212 and 560.255 of the Michigan Compiled Laws, shall be a sufficient legal description.

(b) The name, address, and capacity of the owner or lessee of the real property contracting for the improvement.

(c) The name and address of the fee owner of the real property, if the person contracting for the improvement is a land contract vendee or lessee.

(d) The name and address of the owner’s or lessee’s designee.

(e) The name and address of the general contractor, if any. The notice of commencement form shall contain the following caption below the line for the general contractor’s name and address: (the name of the person with whom you have contracted to provide substantially all the improvements to the property.)

(f) The following statement in boldface type on the front of the form:

WARNING TO HOMEOWNER

Michigan law requires that you do the following:

1. Complete and return this form to the person who asked for it within 10 days after the date of the postmark on the request.

2. If you do not complete and return this form within the 10 days you may have to pay the expenses incurred in getting the information.

3. If you do not live at the site of the improvement, you must post a copy of this form in a conspicuous place at that site.

You are not required to but should do the following:

1. Complete and post a copy of this form at the place where the improvement is being made, even if you live there.

2. Make and keep a copy of this form for your own records.

(g) The following statement:

“To lien claimants and subsequent purchasers:

Take notice that work is about to commence on an improvement to the real property described in this instrument. A person having a construction lien may preserve the lien by providing a notice of furnishing to the above named designee and the general contractor, if any, and by timely recording a claim of lien, in accordance with law.

A person having a construction lien arising by virtue of work performed on this improvement should refer to the name of the owner or lessee and the legal description appearing in this notice. A person subsequently acquiring an interest in the land described is not required to be named in a claim of lien.

A copy of this notice with an attached form for notice of furnishing may be obtained upon making a written request by certified mail to the above named owner or lessee; the designee; or the person with whom you have contracted.”

(h) The name and address of the person preparing the notice.

(i) An affidavit of the owner or lessee or the agent of the owner or lessee which verifies the notice.

(3) Each copy of the notice of commencement shall have a blank notice of furnishing as described in section 109 attached to it. The blank notice of furnishing shall be easily detachable from the copy of the notice and need not be recorded.

(4) Incorrect information contained in the notice of commencement furnished by or for an owner or lessee shall not affect adversely the rights of a lien claimant as against the property of that owner or lessee.

(5) The owner, lessee, or designee, within 10 days after the date of mailing of a written request by certified mail from a contractor subcontractor, supplier, or laborer, shall prepare and provide a copy of the notice of commencement, together with an attached blank notice of furnishing form, to the contractor, subcontractor, supplier, or laborer requesting a copy of the notice of commencement. A contractor, subcontractor, supplier, or laborer who requests a notice of commencement from an owner or lessee of a residential structure shall supply a blank notice of commencement form together with the attached blank notice of furnishing to the owner or lessee at the time the request is made.

(6) A contractor who has been provided with a notice of commencement from the owner, lessee, or designee, within 10 days after the date of mailing of a written request by certified mail from a subcontractor, supplier, or laborer who has a direct contract with the contractor, shall provide a copy of the notice of commencement, together with an attached blank notice of furnishing form, to the subcontractor, supplier, or laborer requesting a copy of the notice of commencement. If the contractor has not been provided a notice of commencement, the contractor shall provide such subcontractor, supplier, or laborer the name and address of the owner or lessee.

(7) A subcontractor who has been provided with a notice of commencement from the owner, lessee, designee, contractor, or subcontractor, within 10 days after the date of mailing of a written request by certified mail from a subcontractor, supplier, or laborer who has a direct contract with the subcontractor, shall provide a copy of the notice of commencement, together with an attached blank notice of furnishing form, to the subcontractor, supplier, or laborer requesting a copy of the notice of commencement. If the subcontractor has not been provided a notice of commencement, the subcontractor shall provide to such subcontractor, supplier, or laborer, the name and address of the owner or lessee.

(8) If the owner, lessee, or designee has received a blank notice of commencement form pursuant to subsection (5) and if the owner or lessee does not currently reside at the real property described in the notice of commencement, the owner, lessee, or designee shall post a copy of the notice of commencement in a conspicuous place on the real property during the course of the actual physical improvement to the real property.

(9) Failure of the owner, lessee, or designee to provide, upon written request, the notice of commencement, in accordance with this section, shall operate to extend the time within which a subcontractor or supplier may provide a notice of furnishing, as described in section 109, until 20 days after the notice of commencement actually has been furnished to the subcontractor or laborer.

(10) Failure of the owner, lessee, or designee to provide the notice of commencement, in accordance with this section, shall operate to extend the time within which a laborer may provide a notice of furnishing, as described in section 109, until 30 days after the notice of commencement actually has been furnished to the laborer, or until the time in which to provide the notice of furnishing in accordance with section 109 expires, whichever is later.

(11) Failure of the owner, lessee, or designee to post or keep posted a copy of the notice of commencement as provided in subsection (8) shall render the owner or lessee liable to the subcontractor, supplier, or laborer who becomes a lien claimant for all actual expenses sustained by the lien claimant in obtaining the information otherwise provided by the posting.

(12) Failure of a contractor, who has been provided with a notice of commencement from the owner, lessee, or designee, to provide the notice of commencement upon the request of the lien claimant who has a contract with the contractor for an improvement to the property shall render the contractor liable to the lien claimant for all actual expenses sustained by the lien claimant in obtaining the information otherwise provided by the notice of commencement. Failure of a contractor to provide the name and address of the owner or lessee in accordance with subsection (6) shall render the contractor liable to the lien claimant for all actual expenses sustained by the lien claimant in obtaining the name and address of the owner or lessee.

(13) Failure of a subcontractor, who has been provided with a notice of commencement from the owner, lessee, designee, contractor, or subcontractor, to provide the notice of commencement upon the request of a subcontractor, supplier, or laborer who has a direct contract with the subcontractor shall render the subcontractor liable to such subcontractor, supplier, or laborer for all actual expenses sustained by the subcontractor, supplier, or laborer in obtaining the information otherwise provided by the notice of commencement. Failure of a subcontractor to provide the name and address of the owner or lessee in accordance with subsection (6) shall render the subcontractor liable to the lien claimant for all actual expenses sustained by the lien claimant in obtaining the name and address of the owner or lessee.

(14) This section shall only apply to an improvement to a residential structure.

570.1109 Notice of Furnishing, Service

Sec. 109. (1) Except as otherwise provided in sections 108, 108a, and 301, a subcontractor or supplier who contracts to provide an improvement to real property shall provide a notice of furnishing to the designee and the general contractor, if any, as named in the notice of commencement at the address shown in the notice of commencement, either personally or by certified mail, within 20 days after furnishing the first labor or material. If a designee has not been named in the notice of commencement, or if the designee has died, service shall be made upon the owner or lessee named in the notice of commencement. If service of the notice of furnishing is made by certified mail, service is complete upon mailing. A contractor is not required to provide a notice of furnishing to preserve lien rights arising from his or her contract directly with an owner or lessee.

(2) Except as otherwise provided in sections 108 and 108a,, a laborer who contracts to provide an improvement to real property shall provide a notice of furnishing to the designee and the general contractor, if any, as named in the notice of commencement at the address shown in the notice of commencement, either personally or by mail, within 30 days after wages were contractually due but were not paid. If a designee has not been named in the notice of commencement, or if the designee has died, service shall be made upon the owner or lessee named in the notice of commencement. If service of the notice of furnishing is made by mail, service is complete upon mailing by first class mail with postage prepaid.

(3) Except as otherwise provided in sections 108 and 108a, a laborer who provides an improvement to real property shall provide a notice of furnishing to the designee and the general contractor, if any, named in the notice of commencement at the address shown in the notice of commencement, either personally or by certified mail, by the fifth day of the second month following the month in which fringe benefits or withholdings from wages were contractually due but were not paid. If a designee has not been named in the notice of commencement, or if the designee has died, service shall be made upon the owner or lessee named in the notice of commencement. If service of the notice of furnishing is made by certified mail, service is complete upon mailing.

(4) The notice of furnishing, if not given on the form attached to the notice of commencement, shall be in substantially the following form:

NOTICE OF FURNISHING

To: ____________________________________(name of designee (or owner or lessee) from notice of commencement)
___________________________________________________(address from notice of commencement)

Please take notice that the undersigned is furnishing to ______________________________________ (name and address of other contracting party) certain labor or material for __________________ (describe type of work) in connection with the improvement to the real property described in the notice of commencement recorded in liber ____, on page ____ , ____________ (name of county) records, ___________________________________or (a copy of which is attached hereto)

WARNING TO OWNER: THIS NOTICE IS REQUIRED BY THE MICHIGAN CONSTRUCTION LIEN ACT. IF YOU HAVE QUESTIONS ABOUT YOUR RIGHTS AND DUTIES UNDER THIS ACT, YOU SHOULD CONTACT AN ATTORNEY TO PROTECT YOU FROM THE POSSIBILITY OF PAYING TWICE FOR THE IMPROVEMENTS TO YOUR PROPERTY.

____________________________(name and address of lien claimant)
by _________________(name and capacity of party signing for lien claimant)
___________________(address of party signing)
Date: __________

(5) The failure of a lien claimant to provide a notice of furnishing within the time specified in this section shall not defeat the lien claimant’s right to a construction lien for work performed or materials furnished by the lien claimant after the service of the notice of furnishing.

(6) The failure of a lien claimant, to provide a notice of furnishing within the time specified in this section shall not defeat the lien claimant’s right to a construction lien for work performed or materials furnished by the lien claimant before the service of the notice of furnishing except to the extent that payments were made by or on behalf of the owner or lessee to the contractor pursuant to either a contractor’s sworn statement or a waiver of lien in accordance with this act for work performed or material delivered by the lien claimant. This subsection does not apply to a laborer.

(7) The failure of a laborer to provide a notice of furnishing to the designee as required by subsection (2) shall defeat the laborer’s lien for those wages for which the notice of furnishing is required.

(8) The failure of a laborer to provide a notice of furnishing to the designee as required by subsection (3) shall defeat the laborer’s lien for those fringe benefits and withholdings for which the notice of furnishing is required.

(9) The failure of a laborer to provide a notice of furnishing to the general contractor within the time specified in subsection (2) or (3) shall not defeat the laborer’s right to a construction lien, but the laborer shall be liable for any actual damages sustained by the general contractor as a result of the failure.

(10) One or more laborers may authorize an agent to prepare and serve a notice of furnishing in the manner provided in this section. Notice of furnishing under this section may contain the notice of furnishing of more than 1 laborer and shall contain the information required in subsection (4) as to each laborer for whom it is prepared. The notice of furnishing of each lien claimant under this subsection shall be considered by the court on its own merits.

570.1110 Sworn Statement by Contractor, Subcontractor, Owner May Withhold Payment, Direct Payment, Notice to General Contractor, Failure to Provide Sworn Statement, Penalties

Sec. 110. (1) A contractor shall provide a sworn statement to the owner or lessee in each of the following circumstances:

(a) When payment is due to the contractor from the owner or lessee or when the contractor requests payment from the owner or lessee.

(b) When a demand for the sworn statement has been made by or on behalf of the owner or lessee.

(2) A subcontractor shall provide a sworn statement to the owner or lessee when a demand for the sworn statement has been made by or on behalf of the owner or lessee.

(3) A subcontractor shall provide a sworn statement to the contractor when payment is due to the subcontractor from the contractor or when the subcontractor requests payment from the contractor.

(4) The sworn statement shall list each subcontractor and supplier with whom the person issuing the sworn statement has contracted relative to the improvement to the real property. The sworn statement shall contain a list of laborers with whom the person issuing the sworn statement has contracted relative to the improvement to the real property and for whom payment for wages or fringe benefits and withholdings are due but unpaid and the itemized amount of such wages or fringe benefits and withholdings. The sworn statement shall be in substantially the following form:

SWORN STATEMENT

State of Michigan

) ss.
County of _________)__________, being duly sworn, deposes and says: That _______ is the (contractor) (subcontractor) for an improvement to the following described real property situated in ____________ County, Michigan, described as follows:______________________ (insert legal description of property)

That the following is a statement of each subcontractor and supplier and laborer, for which laborer the payment of wages or fringe benefits and withholdings is due but unpaid, with whom the (contractor) (subcontractor) has (contracted) (subcontracted) for performance under the contract with the owner or lessee thereof, and that the amounts due to the persons as of the date hereof are correctly and fully set forth opposite their names, as follows:

Name of

Type of

Total Amount

Amount

Balance Amount

Amount of subcontractor, improvement contract already currently to complete of laborer laborer supplier, furnished price paid owing (optional) wages fringe or laborer due benefits and but unpaid withholdings due but unpaid

___________________________________________________________________
Totals

(Some columns are not applicable to all persons listed)

That the contractor has not procured material from, or subcontracted with, any person other than those set forth above and owes no money for the improvement other than the sums set forth above. Deponent further says that he or she makes the foregoing statement as the (contractor) (subcontractor) or as _______ of the (contractor) (subcontractor) for the purpose of representing to the owner or lessee of the above-described premises and his or her agents that the above-described property is free from claims of construction liens, or the possibility of construction liens, except as specifically set forth above and except for claims of construction liens by laborers which may be provided pursuant to section 109 of the construction lien act, Act No. 497 of the Public Acts of 1980, as amended, being section 570.1109 of the Michigan Compiled Laws.

WARNING TO OWNER: AN OWNER OR LESSEE OF THE ABOVE-DESCRIBED PROPERTY MAY NOT RELY ON THIS SWORN STATEMENT TO AVOID THE CLAIM OF A SUBCONTRACTOR, SUPPLIER, OR LABORER WHO HAS PROVIDED A NOTICE OF FURNISHING OR A LABORER WHO MAY PROVIDE A NOTICE OF FURNISHING PURSUANT TO SECTION 109 OF THE CONSTRUCTION LIEN ACT TO THE DESIGNEE OR TO THE OWNER OR LESSEE IF THE DESIGNEE IS NOT NAMED OR HAS DIED.

____________________Deponent

WARNING TO DEPONENT: A PERSON, WHO WITH INTENT TO DEFRAUD, GIVES A FALSE SWORN STATEMENT IS SUBJECT TO CRIMINAL PENALTIES AS PROVIDED IN SECTION 110 OF THE CONSTRUCTION LIEN ACT, ACT NO. 497 OF THE PUBLIC ACTS OF 1980, AS AMENDED, BEING SECTION 570.1110 OF THE MICHIGAN COMPILED LAWS.

Subscribed and sworn to before me this ______ day of _____, 20 __.

_________________________

Notary Public, ____ County, Michigan.

My commission expires: ____________ .

(5) The contractor or subcontractor shall not be required to list in the sworn statement material furnished by the contractor or subcontractor out of his or her own inventory, and which has not been purchased specifically for the purpose of performing the contract.

(6) After the contractor or subcontractor provides the sworn statement, the owner or lessee may withhold or upon written demand from the contractor shall withhold from the amount which is due or to become due to the contractor or to the subcontractor for work already performed, an amount sufficient to pay all sums which are due to subcontractors or to suppliers or to laborers, as shown by the sworn statement, or which is due to lien claimants who have provided a notice of furnishing pursuant to section 109. From the amount withheld, the owner or lessee may directly pay subcontractors, suppliers, or laborers the amount they are due as shown by the sworn statement. If the contract provides for payments by the owner to the general contractor, if any, in the normal course of construction, but the owner elects to pay lien claimants directly pursuant to this section, the first time the owner elects to make payment directly to a lien claimant he or she shall provide at least 5 business days’ notice to the general contractor of the intention to make direct payment. Subsequent direct disbursements to lien claimants need not be preceded by the 5-day notice provided in this section unless the owner first returns to the practice of paying all sums to the general contractor. As between the owner or lessee and the contractor or subcontractor, all payments made pursuant to this subsection shall be considered the same as if paid directly to the contractor or subcontractor. If an amount is withheld pursuant to this subsection from the contractor or subcontractor, the owner or lessee, upon request, shall prepare and provide to the contractor or subcontractor an itemized statement of the sums withheld. If an amount is paid directly to a lien claimant pursuant to this section, the owner or lessee shall, if requested by the contractor or subcontractor, provide to the contractor or subcontractor an itemized statement of the sums paid.

(7) An owner, lessee, designee, mortgagee, or contractor may rely on a sworn statement prepared by a party other than himself or herself to avoid the claim of a subcontractor, supplier, or laborer unless the subcontractor, supplier, or laborer has provided a notice of furnishing as required by section 109 or unless the notice of furnishing is excused pursuant to section 108 or 108a.

(8) If a contractor fails to provide a sworn statement to the owner or lessee prior to the recording of the contractor’s claim of lien, the contractor’s construction lien shall not be invalid. However, the contractor shall not be entitled to any payment, and a complaint, cross-claim, or counterclaim may not be filed to enforce the construction lien until the sworn statement has been provided.

(9) If a subcontractor fails to provide a sworn statement pursuant to subsection (2) to the owner or lessee prior to the recording of the subcontractor’s claim of lien, the subcontractor’s construction lien shall not be invalid. However, a complaint, cross-claim, or counterclaim may not be filed to enforce the construction lien until the sworn statement has been provided.

(10) A contractor or subcontractor who, with intent to defraud, gives or causes to be given to any owner or lessee, when he or she desires to draw money, a sworn statement as required by this section, which is in fact false, is guilty of a misdemeanor if the statement involved is for $100.00 or less and a felony if it is for more than $100.00.

570.1111 Claim of Lien, Recording, Time

Sec. 111. (1) Notwithstanding section 109, the right of a contractor, subcontractor, laborer, or supplier to a construction lien created by this act shall cease to exist unless, within 90 days after the lien claimant’s last furnishing of labor or material for the improvement, pursuant to the lien claimant’s contract, a claim of lien is recorded in the office of the register of deeds for each county where the real property to which the improvement was made is located. A claim of lien shall be valid only as to the real property described in the claim of lien and located within the county where the claim of lien has been recorded.

(2) A claim of lien shall be in substantially the following form:

CLAIM OF LIEN

Notice is hereby given that on the ____ day of _____, 20__
_____________(name)__________________________(address) first provided labor or material for an improvement to _______________________________, the (legal description of real property from notice of commencement) (owner) (lessee) of which property is _______________________(name of owner or lessee from notice of commencement) The last day of providing the labor or material was the _____ day of _____, 20__

TO BE COMPLETED BY A LIEN CLAIMANT WHO IS A CONTRACTOR, SUBCONTRACTOR, OR SUPPLIER:

The lien claimant’s contract amount, including extras, is $ _______ The lien claimant has received payment thereon in the total amount of $_____, and therefore claims a construction lien upon the above-described real property in the amount of $__________

TO BE COMPLETED BY A LIEN CLAIMANT WHO IS A LABORER:

The lien claimant’s hourly rate, including fringe benefits and withholdings, is $_____. There is due and owing to or on behalf of the laborer the sum of $______ for which the laborer claims a construction lien upon the above-described real property.

________________________(lien claimant)

by ______________________(signature of lien claimant, agent, or attorney)

_________________________(address of party signing claim of lien)

Date: _______________

State of Michigan ss. County of ________________)

Subscribed and sworn to before me this ____ day of ______, 20__

______________________________________Signature of Notary Public _________________

My commission expires: ___________________

Prepared by: _____________________________(name and address of party)

(3) If the claim of lien has been assigned, the claim of lien shall state: “The construction lien having been assigned, this claim of lien is made by ________ as assignee thereof”.

(4) A claim of lien by a subcontractor, supplier, or laborer shall have attached to it a proof of service of a notice of furnishing described in section 109.

(5) Each contractor, subcontractor, supplier, laborer, or agent of a group of laborers authorized under subsection (6) recording a claim of lien, within 15 days after the date of the recording, shall serve on the designee personally or by certified mail, return receipt requested, at the address shown on the notice of commencement, a copy of the claim of lien and a copy of any proof of service recorded in connection with the claim of lien. If a designee has not been named in the notice of commencement, or if the designee has died, service shall be made upon the owner or lessee named in the notice of commencement. If the service is made by certified mail, service is complete upon mailing. Proof of making the service shall be attached to any complaint, cross-claim, or counterclaim filed to enforce a construction lien.

(6) One or more laborers may authorize an agent to prepare, record, and serve a claim of lien in the manner provided in this section. A claim of lien under this section may contain the claim of lien of more than 1 laborer and shall contain the information required in subsection (2) as to each laborer for whom it is prepared. The claim of lien of each lien claimant under this subsection shall be considered by the court on its own merits.

570.1112 Recording, Indexing, Fees

Sec. 112. (1) If a notice of commencement, claim of lien, certificate of discharge of lien, or a certificate of a county clerk that no proceedings to enforce a statement or claim of lien have been commenced within the period provided by law is recorded in the office of a register of deeds, the register shall endorse thereon the date of its recording and shall properly index the instrument.

(2) The fee for recording an instrument described in subsection (1) shall be the same as the fee that is provided by law for the recording of a real estate mortgage.

(3) The recording of a notice of commencement or a claim of lien shall operate as constructive notice to subsequent purchasers or encumbrancers in the same manner as the recording of a real estate mortgage.

570.1113 Inspection and Copying of Contract, Statement of Amount Unpaid, Statement of Labor and Material Furnished and Amount Unpaid

Sec. 113. (1) An owner or lessee who contracts for an improvement, upon receipt of a written demand by a lien claimant, shall make available for inspection and copying to the lien claimant, within 10 days after receipt of the written demand, a copy of the contract for the improvement between the owner or lessee and the contractor, and a written statement of the amount due and unpaid on that date on the contract. Any owner or lessee who fails to make available for inspection and copying a copy of the contract and the written statement of the amount due and unpaid, within 10 days after receipt of a written demand, shall be liable to the lien claimant for all actual damages sustained by the lien claimant due to the failure.

(2) Each lien claimant, upon receipt of a written demand by an owner, lessee, designee, or contractor, shall provide to the owner, lessee, designee, or contractor, within 10 days after receipt of the written demand, a written statement of the amount of labor and material furnished to the date of the statement in connection with the improvement for which a construction lien is claimed, any amount remaining due for the labor and material furnished, and the contractual amount of any work remaining to be performed. A lien claimant who fails to provide a statement within 10 days after receipt of a written demand shall be liable to the owner, lessee, or contractor for actual damages sustained by the owner, lessee, or contractor due to the failure. In addition, the owner, lessee, or contractor, after the expiration of the 10-day period without receipt of the requested statement, shall not be required to honor a request for payment by the lien claimant until the statement has been received by the person who requested it.

570.1114 Contractors License, Notice in Contract

Sec. 114. A contractor shall not have a right to a construction lien upon the interest of any owner or lessee in a residential structure unless the contractor has provided an improvement to the residential structure pursuant to a written contract between the owner or lessee and the contractor and any amendments or additions to the contract also shall be in writing. The contract required by this section shall contain a statement, in type no smaller than that of the body of the contract, setting forth all of the following:

(a) That a residential builder or a residential maintenance and alteration contractor is required to be licensed under article 24 of Act 299 of the Public Acts of 1980, as amended, being sections 339.2401 to 339.2412 of the Michigan Compiled Laws. That an electrician is required to be licensed under Act No. 217 of the Public Acts of 1956, as amended, being sections 338.881 to 338.892 of the Michigan Compiled Laws. That a plumber is required to be licensed under Act No. 266 of the Public Acts of 1929, as amended, being sections 338.901 to 338.917 of the Michigan Compiled Laws.

(b) If the contractor is required to be licensed to provide the contracted improvement, that the contractor is so licensed.

(c) If a license is required, the contractor’s license number.

570.1115 Advance Waiver Prohibited, Waivers of Lien, Partial Waivers, Conditional Waivers, Retainage, Waiver Forms

Sec. 115. (1) A person shall not require, as part of any contract for an improvement, that the right to a construction lien be waived in advance of work performed. A waiver obtained as part of a contract for an improvement is contrary to public policy, and shall be invalid, except to the extent that payment for labor and material furnished was actually made to the person giving the waiver. Acceptance by a lien claimant of a promissory note or other evidence of indebtedness from an owner, lessee, or contractor shall not of itself serve to waive or discharge otherwise valid construction lien rights.

(2) A lien claimant who receives full payment for his or her contract shall provide to the owner, lessee, or designee a full unconditional waiver of lien.

(3) A lien claimant who receives partial payment for his or her contract shall provide to the owner, lessee, or designee a partial unconditional waiver of the lien for the amount which the lien claimant has received, if the owner, lessee, or designee requests the partial unconditional waiver.

(4) A partial conditional waiver of lien or a full conditional waiver of lien shall be effective upon payment of the amount indicated in the waiver.

(5) For purposes of this act, retainage which is not payable under a contract until the happening of a certain event in addition to the providing of an improvement, is not due as of the date of the providing of the improvement.

(6) A waiver of a lien under this section shall be effective when a person makes payment relying on the waiver unless at the time payment was made the person making the payment has written notice that the consideration for the waiver has failed.

(7) An agent who is authorized to prepare and serve a notice of furnishing on behalf of a laborer or group of laborers or an agent who is authorized to prepare, record, and serve a claim of lien on behalf of a laborer or group of laborers is automatically authorized to provide waivers of lien, unless or until the laborer or group of laborers notifies the designee in writing that someone other than a previously authorized agent is duly authorized to provide appropriate waivers. An agent who is authorized to prepare and serve a notice of furnishing or a claim of lien on behalf of a laborer or group of laborers shall be responsible for providing
waivers on behalf of such laborer or laborers pursuant to this section. An agent who is authorized to prepare and serve a claim of lien on behalf of a laborer or group of laborers shall be responsible for providing waivers of lien on behalf of such laborer or laborers pursuant to this section. An individual laborer may also provide waivers pursuant to this section instead of the agent.

(8) The following forms shall be used in substantially the following format in executing waivers of construction liens:

(a) PARTIAL UNCONDITIONAL WAIVER

I/we have a contract with ________ to provide _____ for the (other contracting party) improvement to the property described as ________, and hereby waive my/our construction lien to the amount of $_______, for labor/materials provided through ________________ (date) This waiver, together with all previous waivers, if any, (circle one) does not cover all amounts due to me/us for contract improvement provided through the date shown above.

_______________________________(signature of lien claimant)

Signed on: (date) _____________

Address: ____________________

Telephone: __________________

DO NOT SIGN BLANK OR INCOMPLETE FORMS. RETAIN A COPY.

(b) PARTIAL CONDITIONAL WAIVER

I/we have a contract with ____________ to provide _________ for the (other contracting party improvement to the property described as ____________, and hereby waive my/our construction lien to the amount of $_______, for labor/materials provided through _________________ (date) This waiver, together with all previous waivers, if any (circle one) does not cover all amounts due to me/us for contract improvement provided through the date shown above. This waiver is conditioned on actual payment of the amount shown above.

___________________________________(signature of lien claimant)

Signed on: .(date) _____________________

Address: ____________________________

Telephone: __________________________

DO NOT SIGN BLANK OR INCOMPLETE FORMS. RETAIN A COPY.

(c) FULL UNCONDITIONAL WAIVER

My/our contract with ____________to provide ______ for the (other contracting party) improvement of the property described as: ________________ having been fully paid and satisfied, all my/our construction lien rights against such property are hereby waived and released.

___________________________________(signature of lien claimant)

Signed on: (date) _______________

Address: _______________________

Telephone: ___________________

DO NOT SIGN BLANK OR INCOMPLETE FORMS. RETAIN A COPY.

(d) FULL CONDITIONAL WAIVER

My/our contract with ____________ to provide ________ for the (other contracting party) improvement of the property described as: _______ having been fully paid and satisfied, all my/our construction lien rights against such property are hereby waived and released.

This waiver is conditioned on actual payment of _____________

____________________________________________________(signature of lien claimant)

Signed on: _______________

Address: ________________

(date) _______________

Telephone: _______________

DO NOT SIGN BLANK OR INCOMPLETE FORMS. RETAIN A COPY.

570.1116 Release Bond, Notice, Objection to Surety

Sec. 116. (1) The claim of lien of a contractor, subcontractor, supplier, or laborer may at any time be vacated and discharged if a bond, with the lien claimant as obligee, is filed with the county clerk for the county in which the property covered by the lien is located and a copy is given to the obligee lien claimant. The bond shall be in the penal sum of twice the amount for which the lien is claimed and shall be conditioned on the payment of any sum for which the obligee in the bond may obtain judgment on the claim for which the claim of lien was filed. The bond may be either a cash bond executed by a principal, or a surety bond executed by a principal and a surety company authorized to do business in this state.

(2) Within 10 days after receiving the bond, the county clerk shall notify each lien claimant that a bond has been filed and indicate the amount of the bond and the name of the surety on the bond. The lien claimants shall have 10 days after being notified of the bond within which to file an objection to the sufficiency of the surety on the bond, in which case the county clerk shall not approve the bond until the surety has appeared before the county clerk and answered under oath those questions asked by or on behalf of the lien claimant touching on the surety’s financial responsibility. If an objection to the surety is not filed within the 10 days after being notified of the bond or if the county clerk approves the bond after the questioning of the surety, the county clerk shall at once give to the principal and the obligee named in the bond a certificate that a good and sufficient bond has been filed in accordance with this act. The certificate shall state the names of the obligor and obligee, the amount of the bond, and the description of the property covered by the claim of lien being discharged. Upon the recording of the certificate in the office of the register of deeds where the claim of lien was recorded, the claim of lien of the obligee lien claimant named in the claim of lien shall be discharged. If because of the pendency of proceedings to enforce the claim of lien, a notice of lis pendens has been recorded, the recording of the certificate shall also operate as a discharge of the notice of lis pendens. The obligee may make any obligor on the bond a party to an action to enforce a claim under the bond, and a judgment may be recovered in the action against all or any of the obligors.

(3) In an action brought in connection with the claim of the obligee, the court may do 1 or more of the following:

(a) Order the amount of the bond to be reduced.

(b) Order other or additional surety to be provided.

(c) Grant any other relief the court considers to be equitable.

570.1117 Foreclosure Proceedings, Limitations, Notice of Lis Pendens, Parties, Personal Action

Sec. 117. (1) Proceedings for the enforcement of a construction lien and the foreclosure of any interests subject to the construction lien shall not be brought later than 1 year after the date the claim of lien was recorded.

(2) At the time of commencing an action for the enforcement of a construction lien through foreclosure, the plaintiff shall record a notice of lis pendens with respect to the action in the office of the register of deeds for the county in which the real property involved in the action is located.

(3) As provided in section 111(6), an action to foreclose on a construction lien may be maintained by an agent appointed to represent laborers.

(4) Each person who, at the time of filing the action, has an interest in the real property involved in the action which would be divested or otherwise impaired by the foreclosure of the lien, shall be made a party to the action.

(5) In connection with an action for foreclosure of a construction lien, the lien claimant also may maintain an action on any contract from which the lien arose.

(6) Except as otherwise provided in subsection (1), a lien claimant who has been made a party to an action for foreclosure of a construction lien may enforce his or her own construction lien in the action by a cross-claim or counterclaim, and the owner or lessee may timely join other or potential lien claimants in the action.

(7) In an action brought by a contractor or subcontractor to enforce a construction lien through foreclosure, the complaint, cross-claim, or counterclaim must show that the owner or lessee was provided a sworn statement, if a sworn statement was requested or required, pursuant to section 110.

570.1118 Foreclosure Action, Venue, Trial, Attorneys Fees

Sec. 118. (1) An action to enforce a construction lien through foreclosure shall be brought in the circuit court for the county where the real property described in the claim of lien is located. If the real property is located in more than 1 county or judicial circuit, the action may be brought in any of the counties where the real property is located. An action to enforce a construction lien through foreclosure shall be equitable in nature. A construction lien also may be enforced by a cross-claim or counterclaim timely filed in a pending action involving title to, or foreclosure of mortgages or encumbrances on, real property.

(2) In each action in which enforcement of a construction lien through foreclosure is sought, the court shall examine each claim and defense that is presented, and determine the amount, if any, due to each lien claimant or to any mortgagee or holder of an encumbrance, and their respective priorities. The court may allow reasonable attorneys’ fees to a lien claimant who is the prevailing party. The court also may allow reasonable attorneys’ fees to a prevailing defendant if the court determines the lien claimant’s action to enforce a construction lien under this section was vexatious. Attorneys’ fees allowed under this section shall not be paid from the homeowner construction lien recovery fund creamed under part 2.

570.1119 Priorities, Advances from Construction Loans, Retainage

Sec. 119. (1) Except as otherwise provided by subsection (4), as between parties entitled to claim construction liens under this act, their claims of lien shall be treated as having equal priority.

(2) A construction lien under this act shall take priority over all garnishments for the contract debt made after commencement of the first actual physical improvement, without regard to the date of recording of the claim of lien.

(3) A construction lien arising under this act shall take priority over all other interests, liens, or encumbrances which may attach to the building, structure, or improvement, or upon the real property on which the building, structure, or improvement is erected when the other interests, liens, or encumbrances are recorded subsequent to the first actual physical improvement.

(4) A mortgage, lien, encumbrance, or other interest recorded before the first actual physical improvement to real property shall have priority over a construction lien arising under this act. The priority of the mortgage shall exist as to all obligations secured by the mortgage except for indebtedness arising out of advances made subsequent to the first actual physical improvement. An advance made pursuant to the mortgage, but subsequent to the first actual physical improvement shall have priority over a construction lien if, for that advance, the mortgagee has received a contractor’s sworn statement as provided in section 110, has made disbursements pursuant to the contractor’s sworn statement, and has received waivers of lien from the contractor and all subcontractors, laborers, and suppliers who have provided notices of furnishing. The construction lien of any lien claimant not set forth on the sworn statement upon which an advance was made shall be subordinate to the lien of the mortgage, including the advance, unless prior to the advance the lien claimant has provided the designee with a notice of furnishing if required by section 109 or has recorded a claim of lien. Any advance made after a notice of furnishing has been provided or has been excused as provided in sections 108, 108a, and 109 or a claim of lien has been recorded shall be subordinate to the construction lien of that lien claimant unless prior to the advance the mortgagee has received from that lien claimant either a full unconditional waiver of lien or a partial unconditional waiver of lien for the full amount due the lien claimant as of the date through which the lien is waived as shown on the lien waiver and the date through which the lien is waived as shown on the partial unconditional waiver is within 30 days prior to the advance.

(5) For purposes of this section, retainage which is not payable under a contract until the happening of a certain event in addition to the providing of an improvement, is not due as of the date of the providing of the improvement.

570.1120 Part Performance

Sec. 120. If a lien claimant, by reason of the failure of an owner or lessee to perform the contract, and without fault on the part of the lien claimant, has been prevented from completely performing the contract, the lien claimant shall be entitled to compensation for as much as was performed by the claimant under the contract, in proportion to the price stipulated for complete performance of the whole contract, less any payments made to the lien claimant and also to any additional damages which the lien claimant may be entitled to as a matter of law.

570.1121 Judgment, Sale, Redemption, Deficiency Judgment

Sec. 121. (1) If the court finds that a lien claimant is entitled to a construction lien upon the real property to which he or she furnished an improvement, and the amount adjudged to be due has not been paid, the court may enter a judgment ordering the sale of any interest in the real property, or a part of the real property, to which the construction lien attaches. If the construction lien attaches only to the improvement furnished, the court may order a sale of the improvement. If the court finds that there is an interest in or encumbrance against the real property which is superior to the construction lien being foreclosed, the order for sale shall indicate that fact. The court may order a construction lien satisfied out of the rents, profits, and income from the real property to which the construction lien has attached.

(2) In a judgment of foreclosure, the court may provide for adding to the amount determined to be due any amount paid by any lien claimant, mortgagee, or receiver appointed by the court, after the foreclosure sale and before the expiration of the period of redemption, for taxes assessed against the real property sold or for that portion of the premium of an insurance policy covering the building located on the real property, which premium portion is required to keep the policy in force until the expiration of the period of redemption. After the making of any tax or premium payments, an affidavit with respect to the payments shall be recorded immediately in the office of the register of deeds for the county in which the deed on foreclosure sale was recorded.

(3) In the order for the foreclosure sale, the court shall fix a period for redemption. The period of redemption shall not exceed 4 months. The sale shall be conducted in the same manner as a sale on execution. The sale shall become final, subject to the period of redemption, upon the entry of an order of confirmation by the court. Pursuant to section 119(3) and subject to subsection (1), the foreclosure, upon becoming final, shall vest in the grantee named in the deed all the right, title, and interest in the real property which the owner, co-owner, lessee, or co-lessee whose interest is being foreclosed had at the date of the execution of the contract or at any time thereafter.

(4) The court shall enter a final order directing the distribution of all of the funds obtained from the foreclosure sale in accordance with the priorities of the parties as determined by the court. The court shall adjudicate the rights, if any, of lien claimants to a deficiency judgment against any owner or lessee contracting for an improvement. After the making of all payments directed by the court, any surplus from the proceeds of the sale of property on the foreclosure of a construction lien under this act shall be paid over to the owner, co-owner, lessee, co-lessee, or such other person as may be entitled to the surplus. However, the surplus shall be subject to a subsequent judgment or execution under this act in the same manner as if the surplus was derived from a sale made under the subsequent execution.

(5) If all claims of lien are not ascertained when a sale is ordered, or if for any other reason it is deemed proper to postpone the order of distribution of the proceeds of a sale on foreclosure, the court may direct the party making the sale to bring the proceeds of the sale into court, to be disposed of according to order of the court.

(6) Redemption from a foreclosure sale is complete upon payment of all sums set forth in the judgment of foreclosure, together with any sums due for the payment of taxes or insurance premiums as provided in subsection (2). If there is not a redemption from the foreclosure sale, taxes and insurance premiums paid after the sale shall not be included in any deficiency judgment.

570.1122 Receiver

Sec. 122. (1) If the improvement to the real property is not completed as of the date of commencement of an action in which enforcement of a construction lien through foreclosure is sought or in any action to foreclose a mortgage on the real property on which the incomplete improvement exists, any lien claimant or mortgagee may petition the court for the appointment of a receiver. The petition shall be heard as a motion. A receiver may be appointed by the court upon finding that a substantial unpaid construction lien exists, or that the mortgage on the real property is in default and that the lien claimant, the mortgagee, or both, are likely to sustain substantial loss if the improvement is not completed.

(2) When making an appointment of a receiver under this section, the court shall give consideration to the nominations of the mortgagee and the lien claimant. Any receiver appointed under this section shall be deemed a fiduciary for the benefit of all persons having or claiming interests in the real property, and shall exercise his or her office accordingly.

(3) A receiver shall not be appointed under this section for any residential structure, nor for any apartment building containing 4 or less apartments.

(4) The receiver shall be entitled to possession of the real property upon his or her appointment. Unless otherwise limited by the court, and subject to his or her fiduciary responsibility as provided in this act, the receiver shall have all powers generally exercised by a receiver in a court of equity, including the right to be compensated for his or her services and those of his or her agents and attorneys.

570.1123 Completion of Construction or Sale or by Receiver

Sec. 123. (1) The receiver may petition the court for authority to complete construction of improvements to the real property in full or in part, to borrow money to complete the construction, and to grant security, by way of mortgage or otherwise, for the borrowings. The priority of the security shall be determined by the court. A petition for authority to complete construction of improvements shall not be granted unless the court finds that the value added to the real property which will result from the construction is likely to exceed the cost of the additional construction, including all estimated overhead and administrative costs, together with interest on any funds that are to be borrowed for the construction. The receiver also may be authorized by the court to borrow funds for other purposes, including such purposes as preserving and operating the real property.

(2) The receiver may petition the court for authority to sell the real property interest under foreclosure for cash or on other terms as may be ordered by the court. The sale may be by private or public sale and shall be held in the manner directed by the court. A sale under this subsection shall become final upon the entry of an order of confirmation by the court, unless the court allows a period for redemption. The redemption period, if allowed, shall not exceed 4 months.

(3) Any lien claimant or mortgagee may purchase the real property at a sale on foreclosure or a sale by the receiver, and may apply on the purchase price any sums which would be payable to him or her from the proceeds of the sale.

(4) Pursuant to section 119(3) and subject to section 121(1), a sale by the receiver, upon becoming final, shall vest in the grantee named in the deed all the right, title, and interest in the real property which the owner, co-owner, lessee, or co-lessee whose interest is being foreclosed had at the date of the execution of the contract for the improvement or at any time thereafter.

570.1124 Final Account of Receiver

Sec. 124. (1) Upon the completion of the sale of the real property, the receiver shall prepare and submit a final account for examination and approval by the court. The court shall enter a final order directing the distribution of all funds or other assets held by the receiver. Repayment of funds borrowed by the receiver, under court authority, for the completion of improvements, or for any other purpose shall have priority in the distribution, unless a different priority has been ordered by the court. The next priority shall be that of funds expended by the receiver, including his or her fees and those of his or her attorneys and agents. The remaining funds shall be distributed to the parties in the order of the priority of their respective liens, encumbrances, or other rights as determined by the court. The court shall adjudicate the right, if any, to a deficiency judgment against any contracting party.

(2) Each person who appeared in the foreclosure action shall receive a notice of hearing on any court action concerning the receivership.

570.1125 Liens Assignable

Sec. 125. A construction lien which arises under this act is assignable. Proceedings for the enforcement of the lien may be maintained by, and in the name of, the assignee. In that case, the assignee shall have the same power to enforce the construction lien, and shall be subject to the same obligations, as if the proceedings were being taken by, and in the name of, the lien claimant.

570.1126 Limitations on Condominium Liens

Sec. 126. (1) A construction lien, concerning a condominium, arising under this act is subject to the following limitations:

(a) Except as otherwise provided in this section, a construction lien for an improvement furnished to a condominium unit or to a limited common element shall attach only to the condominium unit to which the improvement was furnished.

(b) A construction lien for an improvement authorized by the developer of a condominium project and performed upon the common elements shall attach only to condominium units owned by the developer at the time of recording of the claim of lien.

(c) A construction lien for an improvement authorized by the association of co-owners of condominium units shall attach to each condominium unit only to the proportional extent that the co-owner of the condominium unit is required to contribute to the expenses of administration, as provided by the condominium documents.

(d) A construction lien shall not arise or attach to a condominium unit for work performed on the common elements, if the work was not contracted for by the developer or the association of co-owners of condominium units.

(2) This section shall be subject to the definitions and limitations of Act No. 59 of the Public Acts of 1978, being sections 559.101 to 559.272 of the Michigan Compiled Laws.

570.1127 Discharge of Lien

Sec. 127. (1) When any claim of lien has been fully paid, the lien claimant shall deliver to the owner, lessee, or other person making payment a certificate, witnessed and acknowledged in the same manner as a discharge of mortgage, that the claim has been paid and is now discharged. If an action to enforce the construction lien through foreclosure is pending, the lien claimant also shall furnish, upon request, those documents which are necessary to effect a discontinuance or dismissal of the action and a discharge of any notice of lis pendens filed in connection with the action.

(2) An agent who is authorized to prepare and serve a notice of furnishing on behalf of a laborer or group of laborers or an agent who is authorized to prepare, record, and serve a claim of lien on behalf of a laborer or group of laborers is automatically authorized to provide discharges of lien and other documents described in subsection (1), unless or until the laborer or group of laborers notifies the designee in writing that someone other than a previously authorized agent is duly authorized to provide the appropriate documents. An agent who is authorized to prepare and serve a notice of furnishing or a claim of lien on behalf of a laborer or group of laborers shall be responsible for providing discharges of lien and the other documents described in subsection (1) on behalf of such laborer or laborers pursuant to this section. An agent who is authorized to prepare and serve a claim of lien on behalf of a laborer or group of laborers shall be responsible for providing discharges of lien and the other documents described in subsection (1) on behalf of such laborer or laborers pursuant to this section. An individual laborer may also provide discharges of lien and the other documents described in subsection (1) pursuant to this section instead of the agent.

570.1128 Certificate That No Foreclosure Proceedings Have Been Commenced

Sec. 128. If any statement or claim of lien has been recorded in the office of a register of deeds, and the time within which proceedings to enforce the lien through foreclosure has elapsed without commencement of the proceedings, a person with an interest in the real property affected by the lien, or that person’s agent or attorney, may make and present to the county clerk of the county in which the statement or claim of lien was recorded, an affidavit showing the time when the statement or claim of lien was recorded and the names of the parties to the statement or claim of lien. The county clerk shall examine the records of his or her office, and if it appears that proceedings to enforce the lien have not been commenced with the time provided by law, the county clerk shall execute and deliver to the owner a certificate of that fact, bearing the seal of the circuit court. The certificate may be recorded in the office of the register of deeds for the county where the statement or claim of lien was recorded, after which the statement or claim of lien shall have no effect.

PART 2

570.1201 Homeowner Construction Lien Recovery Fund, Fees

Sec. 201. (1) A homeowner construction lien recovery fund is created within the department of licensing and regulation. The fund shall be self-supporting and shall consist of assessments charged in the following manner:

(a) Except as provided in subsection (4), when applying for renewal licensure for 1982 and when applying for initial licensure, each of the following persons shall be assessed in addition to the license fee, a fee of $50.00 for deposit in the fund:

(i) A person applying for a residential builders license or a residential maintenance and alteration contractor’s license under article 24 of the occupational code, Act No. 299 of the Public Acts of 1980, as amended, being sections 339.2401 to 339.2412 of the Michigan Compiled Laws.
(ii) A person applying for an electrical contractor’s license under the electrical administrative act, Act No. 217 of the Public Acts of 1956, as amended, being sections 338.881 to 338.892 of the Michigan Compiled Laws.
(iii) A person applying for an authorized master plumber’s license under Act No. 266 of the Public Acts of 1929, as amended, being sections 338.901 to 338.917 of the Michigan Compiled Laws, which license authorizes the securing of plumbing installation permits.
(iv) A person applying for a license under the mechanical contractors act.

(b) A laborer who seeks to recover from the fund shall not be required to pay a fee until he or she obtains a recovery from the fund, at which time a fee of $15.00 shall be withheld by the fund from the laborer’s final recovery. However, in no event shall the total amount withheld by the fund from a laborer in a 1-year period exceed $50.00.

(c) Except for persons described in subdivisions (a) and (b), all other lien claimants may become members of the fund by paying a fee of $50.00 prior to the date of the lien claimant’s contract for the improvement to the residential structure. A lien claimant under this subdivision shall not pay a fee of more than $50.00 in a calendar year.

(2) If, on December 1 of any year, the balance in the fund is less than $1,000,000.00, the director of licensing and regulation may require an additional assessment or payment, not to exceed $50.00, from each of the persons described in subsection (1)(a) and (c), unless, within 30 legislative days after the director requires an additional assessment, the legislature, by majority vote of the members elected and serving in both houses by record roll call vote, adopts a concurrent resolution to prohibit the additional assessment. As used in this subsection “legislative day” means a day on which the senate and house is called to order and a quorum of the senate and house is present.

(3) A person shall not be entitled to recover from the fund unless he or she has paid into the fund as required by this section.

(4) Notwithstanding subsection (1)(a), a person shall not be assessed more than $50.00 in an assessment period regardless of the number of licenses applied for or held.

570.1202 Management, Audit

Sec. 202. (1) The director of licensing and regulation shall manage the affairs of the fund pursuant to this act. A detailed financial statement of the condition of the fund shall be published by the director annually. This fund shall be subject to an audit by the auditor general. The state treasurer shall deposit or invest money from the fund, in the same manner and subject to all provisions of law with respect to the deposit or investment of state funds by the state treasurer, and interest earned shall be credited to the fund. The unexpended fund balance shall carry forward to the new fiscal year at the end of each fiscal year.

(2) The department may employ such office clerical and professional help and claims investigators as are necessary to carry out the provisions of this act. The attorney general shall assign members of his or her staff and may supplement that staff by contracting with those private attorneys as are necessary to adequately defend the actions against the fund. All wages, professional fees, and other administrative expenditures necessary for operation and defense of the fund including legal counsel shall be charged to and payable from the fund. Except as provided in subsection (3), wages, professional fees, and other administrative expenditures necessary for the operation of the fund shall not exceed 20% of funds collected by the fund in the previous fiscal year.

(3) If the $50.00 fee is not assessed against license applications and renewals during a year under section 201, the limitation on fund expenditures provided in subsection (2) shall be calculated on the basis of the closest previous year in which the $50.00 fee was assessed and collected for license application and renewals under section 201.

570.1203 Homeowner Affidavit, Recovery from the Fund, Defense by Attorney General

Sec. 203. (1) A claim of construction lien shall not attach to a residential structure, to the extent payments have been made, if the owner or lessee files an affidavit with the court indicating that the owner or lessee has done all of the following:

(a) Paid the contractor for the improvement to the residential structure and the amount of the payment.

(b) Not colluded with any person to obtain a payment from the fund.

(c) Cooperated and will continue to cooperate with the department in the defense of the fund.

(2) In the absence of a written contract pursuant to section 114, the filing of an affidavit under this section shall create a rebuttable presumption that the owner or lessee has paid the contractor for the improvement. The presumption may be overcome only by a showing of clear and convincing evidence to the contrary.

(3) Subject to section 204, a person who has recorded a claim of lien and who is precluded from recovering a construction lien under subsection (1) may recover from the fund the amount for which the lien is established. A person who seeks recovery from the fund shall establish all of the following:

(a) That he or she would be entitled to a construction lien on a residential structure except for the defense provided in subsection (1).

(b) That payment was made by the owner or lessee to the contractor or subcontractor.

(c) That the contractor or subcontractor has retained or used the proceeds or any part of the proceeds paid to the contractor or subcontractor without having paid the person claiming the construction lien.

(d) That he or she has complied with section 201.

(e) That he or she has not colluded with another person to obtain a payment from the fund.

(f) That he or she has complied with any applicable licensing acts.

(g) That he or she has made a reasonable effort to obtain payment from the contractor or subcontractor.

(h) That the contractor or the subcontractor, with whom the person claiming the construction lien contracted with, is licensed if required by law to be licensed.

(4) A subcontractor, supplier, or laborer who seeks enforcement of a construction lien on a residential structure through foreclosure shall join the fund as a defendant in the foreclosure action, and a summons and complaint shall be served on the director by certified or registered mail, or by leaving a copy thereof at the office of the director. The failure to serve a summons and complaint upon the fund shall constitute a bar to recovery from the fund. After service upon the defendant of a summons and complaint in an action in which enforcement of a construction lien through foreclosure is sought, the department may intervene in the action as a party defendant with respect to other construction liens.

(5) The attorney general shall make every reasonable effort to defend the fund and may assert any defense to a claim of lien that would have been available to the owner or lessee.

(6) Payment from the fund shall be made only if the court finds that a subcontractor, supplier, or laborer is entitled to payment from the fund. Subject to section 204, after the judgment has become final the department shall pay the amount of the judgment out of the fund.

570.1204 Payments from the Fund

Sec. 204. The department shall not pay out of the fund to subcontractors, suppliers, and laborers more than $75,000.00 per residential structure. When it appears that the amount claimed from the fund, with respect to a residential structure, will exceed $75,000.00, the department may delay payment until the total amount to be paid can be ascertained. If the total amount payable to subcontractors, suppliers, and laborers exceeds $75,000.00, they shall be paid their proportional shares of that amount.

570.1205 Immunity, Recoupment

Sec. 205. (1) This state and any of its officers or employees in the administration of this act shall not be personally liable to any subcontractor, supplier, or laborer for payment of any sum found to be owing in connection with a contract for the improvement of a residential structure, except from the fund.

(2) If a payment is made by the department from the fund, the department shall be subrogated to the rights of the person to whom the payment was made, and the department may maintain an action in its own name against the contractor or subcontractor who did not pay the claimant receiving the payment from the fund. Any amount recovered by the department shall be deposited in the state treasury to the credit of the fund.

570.1206 Disciplinary Proceedings

Sec. 206. If the department makes a payment from the fund as the result of a licensee’s failure to pay a lien claimant, the department shall enter a complaint against the licensee with the appropriate licensing agency to be addressed by the disciplinary proceedings under the appropriate licensing law.

570.1207 False Information, Felony

Sec. 207. A person who submits false information to receive a payment from the fund is guilty of a felony.

PART 3

570.1301 Residential Structures, Application of Act, Statement of Date of Contract, Notice of Furnishing, Definitions

Sec. 301. (1) With respect to residential structures, this act shall control all rights to a construction lien arising from any project for which the contracting owner entered the first contract with a contractor on or after January 1, 1982.

(2) With respect to residential structures, Act No. 179 of the Public Acts of 1891, as amended, being sections 570.1 to 570.30 of the Michigan Compiled Laws, shall control all rights to a lien arising from any project for which the contracting owner entered the first contract with a contractor before January 1, 1982.

(3) Except as provided in subsection (1), this act shall control all rights to a construction lien arising from any project for which the contracting owner entered the first contract with a contractor on or after March 1, 1982.

(4) Except as provided in subsection (2), Act No. 179 of the Public Acts of 1891, as amended, being sections 570.1 to 570.30 of the Michigan Compiled Laws, shall control all rights to a lien arising from any project for which the contracting owner entered the first contract with a contractor before March 1, 1982.

(5) A contractor, subcontractor, supplier, or laborer may, by certified mail to the owner or designee, request in writing a statement as to the date of the owner’s first contract with a contractor on the project. The owner or designee addressed shall respond by return mail within 10 days of the postmark of such request. The lien claimant may rely upon the information so provided in determining the applicable and controlling state law. Failure of the owner, lessee, or designee to respond to the request within the 10 days shall operate to extend the time within which:

(a) A subcontractor or supplier may provide a notice of furnishing, as described in section 109, until 20 days after the information actually has been furnished to the subcontractor or supplier.

(b) A laborer may provide a notice of furnishing, as described in section 109, until 90 days after the information actually has been furnished to the laborer.

(6) As used in this section:

(a) “Contractor” does not include a supplier, nor relate to a contract solely for preparation for the actual physical improvement such as surveying, soil boring and testing, architectural or engineering planning, or the preparation of other plans or drawings of any kind or nature.

(b) “Project” means the aggregate of improvements contracted for by the contracting owner.

570.1302 Liberal Construction

Sec. 302. (1) This act is declared to be a remedial statute, and shall be liberally construed to secure the beneficial results, intents, and purposes of this act. Substantial compliance with the provisions of this act shall be sufficient for the validity of the construction liens provided for in this act, and to give jurisdiction to the court to enforce them.

(2) This act shall not be construed to prevent a lien claimant from maintaining a separate action on a contract.

570.1304 Joint Review Committee

Sec. 304. (1) The legislature shall create a joint review committee composed of members of the standing committee responsible for the consideration of construction lien legislation in each house and members of the legislative council. The joint review committee shall initiate a review of the functions, responsibilities, and performance of the fund not later than February 1, 1985.

(2) The joint review committee shall report to the legislature not later than September 30, 1985, recommending continuation, termination, or alteration of the fund.

570.1305 Effective Date

Sec. 305. (1) Except as provided in subsection (2), this act shall take effect January 1, 1982.